Installation steps of steel structure plant Hill Wall

The installation of the mountain wall of the steel structure plant is divided into five steps.

First, install the folded angle steel on the starting side for fixing the flashing to the slope.

Next, Install full-length flashing and sliding bearings;

Installation of metal hangers for reliable fixing of the flashing to the angle and for its expansion and contraction.

Installation of metal roof panels and sliding bearings.

Installation of flashing on the hill wall and inner siding panels on the  parapet wall.